AI Insights
Fitweld's own numbers, read every night and turned into a short list of decisions. Each one shows the money involved and what to do about it. Nothing here needs a spreadsheet.
Priority actions
7
4 need attention today
Cash to collect
$2.07M
claimable across live jobs
Overdue now
$168k
chase first
Reads run
Nightly
6:00am, on your data
Lutheran Aged Care Expansion is tracking over contract
61% of the cost budget is spent at 46% built. On the current run-rate it finishes near $209,348 against a $196,000 contract, about -7% margin versus 19% planned.
Get the $5,100 of pending variations approved and claimed before the next progress claim.
88% confidenceBeechworth Health Plant Platform margin is being squeezed
46% of the cost budget is spent at 38% built. On the current run-rate it finishes near $117,368 against a $118,000 contract, about 1% margin versus 18% planned.
Review hours booked and raise a variation for any out-of-scope work.
82% confidence310UC96.8 is out of stock
You're down to zero 310 UC 96.8 kg/m Grade 300. Christmont Winery Pods (22 t) starts in 6 days and columns like this are on its cutting list. Merchant lead time runs 2 to 3 weeks.
Raise a purchase order to InfraBuild or Liberty now so steel lands before the job hits the floor.
91% confidence$168,000 overdue from Joss Group
Joss Group is past their 45 EOM terms and is also your largest live account with 3 jobs on the go. It's the single biggest thing you can do for July cash.
Chase the overdue claim before the next Westmont claim goes out.
94% confidenceCleat Bracket Set is out at the galvaniser
160 Cleat Bracket Set for Ausco Modular (PO-AUS-2228) are at Alpine galvanising, due to ship in 9 days.
Chase Alpine on the return date, or the ship date on PO-AUS-2228 slips.
89% confidenceMazda Motor Showroom has no slack before erection
Fabrication of the canopy screens finishes the same week install crew A is booked to erect the frame, and the handover is locked to 24 July. One weather day at Westmont pushes it out.
Protect the CNC slot, or move the canopy screens to the Pakenham bay to build a buffer.
76% confidenceGood chance on Wangaratta Aerodrome Hangar Frame
$596,000 quote to North East Building Co, who you've delivered 1 job for before. A decision is expected in 24 days.
Call North East Building Co this week to keep it warm while it's fresh.
68% confidenceProjected cash in, next four weeks
From progress claims due on live jobs
What's next
- Best-fit quote pricing, learned from your last three years of won and lost jobs.
- Steel demand forecasting so stock is ordered before a job hits the floor.
- Labour planning that reads the schedule and flags a short week early.
Built on the same data you already have. No new systems to run.