Margin Act now FW-2026-0148 →

Lutheran Aged Care Expansion is tracking over contract

61% of the cost budget is spent at 46% built. On the current run-rate it finishes near $209,348 against a $196,000 contract, about -7% margin versus 19% planned.

Get the $5,100 of pending variations approved and claimed before the next progress claim.

88% confidence
Margin Act now FW-2026-0149 →

Beechworth Health Plant Platform margin is being squeezed

46% of the cost budget is spent at 38% built. On the current run-rate it finishes near $117,368 against a $118,000 contract, about 1% margin versus 18% planned.

Review hours booked and raise a variation for any out-of-scope work.

82% confidence
Materials Act now Purchasing →

310UC96.8 is out of stock

You're down to zero 310 UC 96.8 kg/m Grade 300. Christmont Winery Pods (22 t) starts in 6 days and columns like this are on its cutting list. Merchant lead time runs 2 to 3 weeks.

Raise a purchase order to InfraBuild or Liberty now so steel lands before the job hits the floor.

91% confidence
Cash flow Act now Clients →

$168,000 overdue from Joss Group

Joss Group is past their 45 EOM terms and is also your largest live account with 3 jobs on the go. It's the single biggest thing you can do for July cash.

Chase the overdue claim before the next Westmont claim goes out.

94% confidence
Production Watch PRD-2026-0038 →

Cleat Bracket Set is out at the galvaniser

160 Cleat Bracket Set for Ausco Modular (PO-AUS-2228) are at Alpine galvanising, due to ship in 9 days.

Chase Alpine on the return date, or the ship date on PO-AUS-2228 slips.

89% confidence
Schedule Watch Schedule →

Mazda Motor Showroom has no slack before erection

Fabrication of the canopy screens finishes the same week install crew A is booked to erect the frame, and the handover is locked to 24 July. One weather day at Westmont pushes it out.

Protect the CNC slot, or move the canopy screens to the Pakenham bay to build a buffer.

76% confidence
Sales Opportunity QT-2026-0097 →

Good chance on Wangaratta Aerodrome Hangar Frame

$596,000 quote to North East Building Co, who you've delivered 1 job for before. A decision is expected in 24 days.

Call North East Building Co this week to keep it warm while it's fresh.

68% confidence

Projected cash in, next four weeks

From progress claims due on live jobs

$186k
This wk
$142k
Wk 2
$208k
Wk 3
$164k
Wk 4
Phase 2

What's next

  • Best-fit quote pricing, learned from your last three years of won and lost jobs.
  • Steel demand forecasting so stock is ordered before a job hits the floor.
  • Labour planning that reads the schedule and flags a short week early.

Built on the same data you already have. No new systems to run.