Lutheran Aged Care Expansion

Joss Group · Albury NSW · PM Kate Nguyen · 34 t

Fabrication Due 08 Aug 2026
1 Won
2 Detailing
3 Fabrication
4 Surface Treatment
5 Ready to Dispatch
6 Installing
7 Complete

Job profitability, cost vs contract

19% margin

Contract (ex-GST)

$196,000

Committed cost

$158,000

Margin

$38,000

Steel & sections $66,360
Fabrication labour $44,240
Surface treatment $12,640
Site install $22,120
Detailing & freight $12,640
Margin $38,000

Billing (Xero)

Contract ex-GST
$196,000
GST (10%)
$19,600
Total inc-GST
$215,600
Invoiced to date
$78,000
Remaining to bill
$118,000
Progress
46%

Variations

$4,600 approved, $5,100 pending
  • VO-01 Extra hot dip galvanising to handrails (spec change) $4,600 Approved
  • VO-02 Additional wall bracing per engineer RFI-08 $5,100 Pending

Progress claim

Original contract
$196,000
Approved variations
$4,600
Adjusted contract
$200,600
Claimed to date
$78,000
Retention held (5%)
$3,900
This claim (46%)
$14,276
Generate progress claim

Workshop, work orders (3)

  • WO-4802

    Wall frames RHS

    Bay 1 · Lucas Petrovic

    9/20 Welding
  • WO-4812

    Lintels & headers (PFC)

    CNC · Ryan Doyle

    6/22 Cutting
  • WO-4803

    Roof beams 360UB

    Bay 1 · Wayne Ellis

    4/12 Fit-up

Purchasing, steel POs (1)

  • PO-2026-0224

    Southern Steel Group

    RHS/SHS, Lutheran Aged Care

    $14,900 Ordered

Quality (ISO 9001)

ITP 40% complete

NCRs

  • NCR-2026-011 Open

    Galv coating thickness below spec on handrail

Material certs (mill certs)

No heats recorded yet.