Lutheran Aged Care Expansion
Joss Group · Albury NSW · PM Kate Nguyen · 34 t
Fabrication
Due 08 Aug 2026
1 Won
2 Detailing
3 Fabrication
4 Surface Treatment
5 Ready to Dispatch
6 Installing
7 Complete
Job profitability, cost vs contract
19% marginContract (ex-GST)
$196,000
Committed cost
$158,000
Margin
$38,000
Steel & sections $66,360
Fabrication labour $44,240
Surface treatment $12,640
Site install $22,120
Detailing & freight $12,640
Margin $38,000
Billing (Xero)
- Contract ex-GST
- $196,000
- GST (10%)
- $19,600
- Total inc-GST
- $215,600
- Invoiced to date
- $78,000
- Remaining to bill
- $118,000
- Progress
- 46%
Variations
$4,600 approved, $5,100 pending- VO-01 Extra hot dip galvanising to handrails (spec change) $4,600 Approved
- VO-02 Additional wall bracing per engineer RFI-08 $5,100 Pending
Progress claim
- Original contract
- $196,000
- Approved variations
- $4,600
- Adjusted contract
- $200,600
- Claimed to date
- $78,000
- Retention held (5%)
- $3,900
- This claim (46%)
- $14,276
Workshop, work orders (3)
- WO-4802
Wall frames RHS
Bay 1 · Lucas Petrovic
9/20 Welding - WO-4812
Lintels & headers (PFC)
CNC · Ryan Doyle
6/22 Cutting - WO-4803
Roof beams 360UB
Bay 1 · Wayne Ellis
4/12 Fit-up
Purchasing, steel POs (1)
- PO-2026-0224
Southern Steel Group
RHS/SHS, Lutheran Aged Care
$14,900 Ordered
Quality (ISO 9001)
ITP 40% completeNCRs
- NCR-2026-011 Open
Galv coating thickness below spec on handrail
Material certs (mill certs)
No heats recorded yet.