Fitweld Engineering
Xero · synced 8:14am

Lutheran Aged Care Expansion

Joss Group · Albury NSW · PM Kate Nguyen · 34 t

Fabrication Due 08 Aug 2026
1 Won
2 Detailing
3 Fabrication
4 Surface Treatment
5 Installing
6 Complete

Job profitability — live cost vs contract

19% margin

Contract (ex-GST)

$196,000

Committed cost

$158,000

Margin

$38,000

Steel & sections $66,360
Fabrication labour $44,240
Surface treatment $12,640
Site install $22,120
Detailing & freight $12,640
Margin $38,000

Billing (Xero)

Contract ex-GST
$196,000
GST (10%)
$19,600
Total inc-GST
$215,600
Invoiced to date
$78,000
Remaining to bill
$118,000
Progress
46%

Workshop — work orders (1)

  • WO-4802

    Wall frames RHS

    Bay 1 · Lucas Petrovic

    9/20 Welding

Purchasing — steel POs (1)

  • PO-2026-0224

    Southern Steel Group

    RHS/SHS — Lutheran Aged Care

    $14,900 Ordered

Quality (ISO 9001)

ITP 40% complete

NCRs

  • NCR-2026-011 Open

    Galv coating thickness below spec on handrail

Material certs (mill certs)

No heats recorded yet.