Beechworth Health Plant Platform
Searle Bros Constructions · Beechworth VIC · PM Kate Nguyen · 19 t
Fabrication
Due 22 Aug 2026
1 Won
2 Detailing
3 Fabrication
4 Surface Treatment
5 Ready to Dispatch
6 Installing
7 Complete
Job profitability, cost vs contract
18% marginContract (ex-GST)
$118,000
Committed cost
$97,000
Margin
$21,000
Steel & sections $40,740
Fabrication labour $27,160
Surface treatment $7,760
Site install $13,580
Detailing & freight $7,760
Margin $21,000
Billing (Xero)
- Contract ex-GST
- $118,000
- GST (10%)
- $11,800
- Total inc-GST
- $129,800
- Invoiced to date
- $44,000
- Remaining to bill
- $74,000
- Progress
- 38%
Variations
$0 approvedNo variations raised on this job.
Progress claim
- Original contract
- $118,000
- Approved variations
- $0
- Adjusted contract
- $118,000
- Claimed to date
- $44,000
- Retention held (5%)
- $2,200
- This claim (38%)
- $840
Workshop, work orders (2)
- WO-4795
Access platform & handrail
Bay 1 · Ellie Watts
4/12 QA Hold - WO-4796
Cable ladder supports
Bay 2 · Sam Okafor
7/16 Welding
Purchasing, steel POs (0)
No purchase orders raised yet.
Quality (ISO 9001)
ITP 30% completeNCRs
No non-conformances raised.
Material certs (mill certs)
No heats recorded yet.