Ablett Pavilion Staircase
Myrtleford Football Netball Club · Myrtleford VIC · PM Kate Nguyen · 6 t
Complete
Due 30 Apr 2026
1 Won
2 Detailing
3 Fabrication
4 Surface Treatment
5 Ready to Dispatch
6 Installing
7 Complete
Job profitability, cost vs contract
21% marginContract (ex-GST)
$42,000
Final cost
$33,200
Margin
$8,800
Steel & sections $13,944
Fabrication labour $9,296
Surface treatment $2,656
Site install $4,648
Detailing & freight $2,656
Margin $8,800
Billing (Xero)
- Contract ex-GST
- $42,000
- GST (10%)
- $4,200
- Total inc-GST
- $46,200
- Invoiced to date
- $42,000
- Remaining to bill
- $0
- Progress
- 100%
Variations
$0 approvedNo variations raised on this job.
Progress claim
- Original contract
- $42,000
- Approved variations
- $0
- Adjusted contract
- $42,000
- Claimed to date
- $42,000
- Retention held (5%)
- $2,100
- This claim (100%)
- $0
Workshop, work orders (0)
No work orders yet, job still in detailing.
Purchasing, steel POs (0)
No purchase orders raised yet.
Quality (ISO 9001)
ITP 100% completeNCRs
No non-conformances raised.
Material certs (mill certs)
No heats recorded yet.