Progress Claim

Claim No. 5

Date of claim

01 July 2026

To

Myrtleford Football Netball Club

Club Committee

ABN 77 302 118 664

Myrtleford VIC

Project

Ablett Pavilion Staircase

Job FW-2026-0139

Myrtleford VIC

Structural steel supply, fabricate & install

Description Amount (ex-GST)
Original contract sum$42,000
Approved variations$0
Adjusted contract sum$42,000
Value of work completed to date (100%)$42,000
Less previously claimed($42,000)
Value of this claim$0
Less retention (5%)($0)
Net claim$0
GST (10%)$0
Total due this claim (inc-GST) $0

Payment terms

14 days. Payment due by 31 July 2026.

Retention held after this claim

$2,100 (5% of works)