Fitweld Engineering
Xero · synced 8:14am

Mazda Motor Showroom

Zauner Construction · Wangaratta VIC · PM Dan Kelly · 42 t

Fabrication Due 24 July 2026
1 Won
2 Detailing
3 Fabrication
4 Surface Treatment
5 Installing
6 Complete

Job profitability — live cost vs contract

20% margin

Contract (ex-GST)

$268,000

Committed cost

$214,000

Margin

$54,000

Steel & sections $89,880
Fabrication labour $59,920
Surface treatment $17,120
Site install $29,960
Detailing & freight $17,120
Margin $54,000

Billing (Xero)

Contract ex-GST
$268,000
GST (10%)
$26,800
Total inc-GST
$294,800
Invoiced to date
$120,000
Remaining to bill
$148,000
Progress
55%
From quote QT-2026-0091

Workshop — work orders (4)

  • WO-4821

    Portal columns 200UC (×8)

    Bay 1 · Wayne Ellis

    6/8 Welding
  • WO-4822

    Rafters 360UB (×8)

    Bay 1 · Mitch Farrow

    3/8 Fit-up
  • WO-4823

    Base plates & cleats

    CNC · Ryan Doyle

    22/32 Drilling
  • WO-4824

    Canopy screens (SHS)

    Bay 2 · Ben Hargreaves

    4/18 Cutting

Purchasing — steel POs (1)

  • PO-2026-0212

    InfraBuild Steel

    Sections & cleats — Mazda Showroom

    $38,400 Received

Quality (ISO 9001)

ITP 48% complete

NCRs

  • NCR-2026-013 Closed

    Base plate BP-04 hole spacing 5mm out (detailing)

Material certs (mill certs)

  • H-882041 360UB44.7 Grade 300 On file
  • H-882110 200UC46.2 Grade 300 On file