Progress Claim

Claim No. 3

Date of claim

01 July 2026

To

Zauner Construction

Michael Zauner

ABN 62 004 213 887

Shepparton VIC

Project

Mazda Motor Showroom

Job FW-2026-0137

Wangaratta VIC

Structural steel supply, fabricate & install

Description Amount (ex-GST)
Original contract sum$268,000
Approved variations$8,400
Adjusted contract sum$276,400
Value of work completed to date (55%)$152,020
Less previously claimed($120,000)
Value of this claim$32,020
Less retention (5%)($1,601)
Net claim$30,419
GST (10%)$3,042
Total due this claim (inc-GST) $33,461

Payment terms

30 EOM. Payment due by 31 July 2026.

Retention held after this claim

$7,601 (5% of works)

This claim is made under the Building and Construction Industry Security of Payment Act. Please remit to Fitweld Engineering Pty Ltd. This is a demonstration document.