ABN 48 617 302 559 · ISO 9001:2015
Fitweld Engineering Pty Ltd
26 Gibson Street, Wangaratta VIC 3677
03 5722 3122
enquiries@fitweld.com.au
Claim No. 3
Date of claim
01 July 2026
To
Zauner Construction
Michael Zauner
ABN 62 004 213 887
Shepparton VIC
Project
Mazda Motor Showroom
Job FW-2026-0137
Wangaratta VIC
Structural steel supply, fabricate & install
| Description | Amount (ex-GST) |
|---|---|
| Original contract sum | $268,000 |
| Approved variations | $8,400 |
| Adjusted contract sum | $276,400 |
| Value of work completed to date (55%) | $152,020 |
| Less previously claimed | ($120,000) |
| Value of this claim | $32,020 |
| Less retention (5%) | ($1,601) |
| Net claim | $30,419 |
| GST (10%) | $3,042 |
| Total due this claim (inc-GST) | $33,461 |
Payment terms
30 EOM. Payment due by 31 July 2026.
Retention held after this claim
$7,601 (5% of works)
This claim is made under the Building and Construction Industry Security of Payment Act. Please remit to Fitweld Engineering Pty Ltd. This is a demonstration document.