Wodonga Distribution Warehouse Portals
Nicholson Construction · Wodonga VIC · PM Dan Kelly · 118 t
Won
Due 04 Dec 2026
1 Won
2 Detailing
3 Fabrication
4 Surface Treatment
5 Ready to Dispatch
6 Installing
7 Complete
Job profitability, cost vs contract
19% marginContract (ex-GST)
$628,000
Committed cost
$508,000
Margin
$120,000
Steel & sections $213,360
Fabrication labour $142,240
Surface treatment $40,640
Site install $71,120
Detailing & freight $40,640
Margin $120,000
Billing (Xero)
- Contract ex-GST
- $628,000
- GST (10%)
- $62,800
- Total inc-GST
- $690,800
- Invoiced to date
- $0
- Remaining to bill
- $628,000
- Progress
- 2%
Variations
$0 approvedNo variations raised on this job.
Progress claim
- Original contract
- $628,000
- Approved variations
- $0
- Adjusted contract
- $628,000
- Claimed to date
- $0
- Retention held (5%)
- $0
- This claim (2%)
- $12,560
Workshop, work orders (0)
No work orders yet, job still in detailing.
Purchasing, steel POs (1)
- PO-2026-0221
Liberty Primary Steel
Universal beams & columns, Wodonga Warehouse
$96,200 Ordered
Quality (ISO 9001)
ITP 0% completeNCRs
No non-conformances raised.
Material certs (mill certs)
- H-886740 UB/UC bundle Awaiting