Fitweld Engineering
Xero · synced 8:14am

Wodonga Distribution Warehouse Portals

Nicholson Construction · Wodonga VIC · PM Dan Kelly · 118 t

Won Due 04 Dec 2026
1 Won
2 Detailing
3 Fabrication
4 Surface Treatment
5 Installing
6 Complete

Job profitability — live cost vs contract

19% margin

Contract (ex-GST)

$628,000

Committed cost

$508,000

Margin

$120,000

Steel & sections $213,360
Fabrication labour $142,240
Surface treatment $40,640
Site install $71,120
Detailing & freight $40,640
Margin $120,000

Billing (Xero)

Contract ex-GST
$628,000
GST (10%)
$62,800
Total inc-GST
$690,800
Invoiced to date
$0
Remaining to bill
$628,000
Progress
2%
From quote QT-2026-0094

Workshop — work orders (0)

No work orders yet — job still in detailing.

Purchasing — steel POs (1)

  • PO-2026-0221

    Liberty Primary Steel

    Universal beams & columns — Wodonga Warehouse

    $96,200 Ordered

Quality (ISO 9001)

ITP 0% complete

NCRs

No non-conformances raised.

Material certs (mill certs)

  • H-886740 UB/UC bundle Awaiting