Fitweld Engineering
Xero · synced 8:14am

Benalla Aquatic Centre Roof Trusses

Fairbrother · Benalla VIC · PM Kate Nguyen · 74 t

Detailing Due 30 Oct 2026
1 Won
2 Detailing
3 Fabrication
4 Surface Treatment
5 Installing
6 Complete

Job profitability — live cost vs contract

18% margin

Contract (ex-GST)

$405,000

Committed cost

$331,000

Margin

$74,000

Steel & sections $139,020
Fabrication labour $92,680
Surface treatment $26,480
Site install $46,340
Detailing & freight $26,480
Margin $74,000

Billing (Xero)

Contract ex-GST
$405,000
GST (10%)
$40,500
Total inc-GST
$445,500
Invoiced to date
$0
Remaining to bill
$405,000
Progress
8%
From quote QT-2026-0093

Workshop — work orders (0)

No work orders yet — job still in detailing.

Purchasing — steel POs (1)

  • PO-2026-0223

    Vulcan Steel

    16 & 20mm plate — Benalla trusses

    $27,500 Ordered

Quality (ISO 9001)

ITP 2% complete

NCRs

No non-conformances raised.

Material certs (mill certs)

  • H-885301 20mm Plate Grade 350 On file