Corowa RSL Entry Awning
Joss Group · Corowa NSW · PM Kate Nguyen · 9 t
On Hold
Due 01 July 2026
1 Won
2 Detailing
3 Fabrication
4 Surface Treatment
5 Installing
6 Complete
Job profitability — live cost vs contract
17% marginContract (ex-GST)
$64,000
Committed cost
$53,000
Margin
$11,000
Steel & sections $22,260
Fabrication labour $14,840
Surface treatment $4,240
Site install $7,420
Detailing & freight $4,240
Margin $11,000
Billing (Xero)
- Contract ex-GST
- $64,000
- GST (10%)
- $6,400
- Total inc-GST
- $70,400
- Invoiced to date
- $12,000
- Remaining to bill
- $52,000
- Progress
- 35%
Workshop — work orders (0)
No work orders yet — job still in detailing.
Purchasing — steel POs (0)
No purchase orders raised yet.
Quality (ISO 9001)
ITP 20% completeNCRs
No non-conformances raised.
Material certs (mill certs)
No heats recorded yet.