Corowa RSL Entry Awning
Joss Group · Corowa NSW · PM Kate Nguyen · 9 t
On Hold
Due 26 June 2026
1 Won
2 Detailing
3 Fabrication
4 Surface Treatment
5 Ready to Dispatch
6 Installing
7 Complete
Job profitability, cost vs contract
17% marginContract (ex-GST)
$64,000
Committed cost
$53,000
Margin
$11,000
Steel & sections $22,260
Fabrication labour $14,840
Surface treatment $4,240
Site install $7,420
Detailing & freight $4,240
Margin $11,000
Billing (Xero)
- Contract ex-GST
- $64,000
- GST (10%)
- $6,400
- Total inc-GST
- $70,400
- Invoiced to date
- $12,000
- Remaining to bill
- $52,000
- Progress
- 35%
Variations
$0 approvedNo variations raised on this job.
Progress claim
- Original contract
- $64,000
- Approved variations
- $0
- Adjusted contract
- $64,000
- Claimed to date
- $12,000
- Retention held (5%)
- $600
- This claim (35%)
- $10,400
Workshop, work orders (0)
No work orders yet, job still in detailing.
Purchasing, steel POs (0)
No purchase orders raised yet.
Quality (ISO 9001)
ITP 20% completeNCRs
No non-conformances raised.
Material certs (mill certs)
No heats recorded yet.