Bunnings Wodonga Mezzanine
Kane Constructions · Wodonga VIC · PM Dan Kelly · 47 t
Fabrication
Due 18 July 2026
1 Won
2 Detailing
3 Fabrication
4 Surface Treatment
5 Ready to Dispatch
6 Installing
7 Complete
Job profitability, cost vs contract
21% marginContract (ex-GST)
$231,000
Committed cost
$183,000
Margin
$48,000
Steel & sections $76,860
Fabrication labour $51,240
Surface treatment $14,640
Site install $25,620
Detailing & freight $14,640
Margin $48,000
Billing (Xero)
- Contract ex-GST
- $231,000
- GST (10%)
- $23,100
- Total inc-GST
- $254,100
- Invoiced to date
- $138,000
- Remaining to bill
- $93,000
- Progress
- 62%
Variations
$0 approved, $6,900 pending- VO-01 Additional edge protection to mezzanine $6,900 Pending
Progress claim
- Original contract
- $231,000
- Approved variations
- $0
- Adjusted contract
- $231,000
- Claimed to date
- $138,000
- Retention held (5%)
- $6,900
- This claim (62%)
- $5,220
Workshop, work orders (4)
- WO-4810
Mezzanine beams 410UB
Bay 2 · Sam Okafor
12/16 Welding - WO-4811
Stair stringers & treads
Bay 2 · Jake Trentino
2/5 Fit-up - WO-4826
Handrail & balustrade
Bay 2 · Jake Trentino
5/14 Drilling - WO-4762
Mezzanine edge protection
Bay 1 · Mitch Farrow
9/15 Welding
Purchasing, steel POs (1)
- PO-2026-0219
Stramit
Z200 purlins, Bunnings mezzanine
$18,700 Received
Quality (ISO 9001)
ITP 55% completeNCRs
- NCR-2026-012 Under Review
Mill cert missing for 410UB heat batch
Material certs (mill certs)
- H-884552 410UB53.7 Grade 300 Awaiting