Fitweld Engineering

Bunnings Wodonga Mezzanine

Kane Constructions · Wodonga VIC · PM Dan Kelly · 47 t

Fabrication Due 18 July 2026
1 Won
2 Detailing
3 Fabrication
4 Surface Treatment
5 Ready to Dispatch
6 Installing
7 Complete

Job profitability, cost vs contract

21% margin

Contract (ex-GST)

$231,000

Committed cost

$183,000

Margin

$48,000

Steel & sections $76,860
Fabrication labour $51,240
Surface treatment $14,640
Site install $25,620
Detailing & freight $14,640
Margin $48,000

Billing (Xero)

Contract ex-GST
$231,000
GST (10%)
$23,100
Total inc-GST
$254,100
Invoiced to date
$138,000
Remaining to bill
$93,000
Progress
62%

Variations

$0 approved, $6,900 pending
  • VO-01 Additional edge protection to mezzanine $6,900 Pending

Progress claim

Original contract
$231,000
Approved variations
$0
Adjusted contract
$231,000
Claimed to date
$138,000
Retention held (5%)
$6,900
This claim (62%)
$5,220
Generate progress claim

Workshop, work orders (4)

  • WO-4810

    Mezzanine beams 410UB

    Bay 2 · Sam Okafor

    12/16 Welding
  • WO-4811

    Stair stringers & treads

    Bay 2 · Jake Trentino

    2/5 Fit-up
  • WO-4826

    Handrail & balustrade

    Bay 2 · Jake Trentino

    5/14 Drilling
  • WO-4762

    Mezzanine edge protection

    Bay 1 · Mitch Farrow

    9/15 Welding

Purchasing, steel POs (1)

  • PO-2026-0219

    Stramit

    Z200 purlins, Bunnings mezzanine

    $18,700 Received

Quality (ISO 9001)

ITP 55% complete

NCRs

  • NCR-2026-012 Under Review

    Mill cert missing for 410UB heat batch

Material certs (mill certs)

  • H-884552 410UB53.7 Grade 300 Awaiting