Fitweld Engineering
Xero · synced 8:14am

Bunnings Wodonga Mezzanine

Kane Constructions · Wodonga VIC · PM Dan Kelly · 47 t

Fabrication Due 18 July 2026
1 Won
2 Detailing
3 Fabrication
4 Surface Treatment
5 Installing
6 Complete

Job profitability — live cost vs contract

21% margin

Contract (ex-GST)

$231,000

Committed cost

$183,000

Margin

$48,000

Steel & sections $76,860
Fabrication labour $51,240
Surface treatment $14,640
Site install $25,620
Detailing & freight $14,640
Margin $48,000

Billing (Xero)

Contract ex-GST
$231,000
GST (10%)
$23,100
Total inc-GST
$254,100
Invoiced to date
$138,000
Remaining to bill
$93,000
Progress
62%

Workshop — work orders (2)

  • WO-4810

    Mezzanine beams 410UB

    Bay 2 · Sam Okafor

    12/16 Welding
  • WO-4811

    Stair stringers & treads

    Bay 2 · Jake Trentino

    2/5 Fit-up

Purchasing — steel POs (1)

  • PO-2026-0219

    Stramit

    Z200 purlins — Bunnings mezzanine

    $18,700 Received

Quality (ISO 9001)

ITP 55% complete

NCRs

  • NCR-2026-012 Under Review

    Mill cert missing for 410UB heat batch

Material certs (mill certs)

  • H-884552 410UB53.7 Grade 300 Awaiting