Benalla Retail Frame
Simmie Constructions · Benalla VIC · PM Kate Nguyen · 16 t
Complete
Due 05 June 2026
1 Won
2 Detailing
3 Fabrication
4 Surface Treatment
5 Installing
6 Complete
Job profitability — live cost vs contract
15% marginContract (ex-GST)
$97,000
Final cost
$82,100
Margin
$14,900
Steel & sections $34,482
Fabrication labour $22,988
Surface treatment $6,568
Site install $11,494
Detailing & freight $6,568
Margin $14,900
Billing (Xero)
- Contract ex-GST
- $97,000
- GST (10%)
- $9,700
- Total inc-GST
- $106,700
- Invoiced to date
- $97,000
- Remaining to bill
- $0
- Progress
- 100%
Workshop — work orders (0)
No work orders yet — job still in detailing.
Purchasing — steel POs (0)
No purchase orders raised yet.
Quality (ISO 9001)
ITP 100% completeNCRs
No non-conformances raised.
Material certs (mill certs)
No heats recorded yet.