Fitweld Engineering
Xero · synced 8:14am

Benalla Retail Frame

Simmie Constructions · Benalla VIC · PM Kate Nguyen · 16 t

Complete Due 05 June 2026
1 Won
2 Detailing
3 Fabrication
4 Surface Treatment
5 Installing
6 Complete

Job profitability — live cost vs contract

15% margin

Contract (ex-GST)

$97,000

Final cost

$82,100

Margin

$14,900

Steel & sections $34,482
Fabrication labour $22,988
Surface treatment $6,568
Site install $11,494
Detailing & freight $6,568
Margin $14,900

Billing (Xero)

Contract ex-GST
$97,000
GST (10%)
$9,700
Total inc-GST
$106,700
Invoiced to date
$97,000
Remaining to bill
$0
Progress
100%

Workshop — work orders (0)

No work orders yet — job still in detailing.

Purchasing — steel POs (0)

No purchase orders raised yet.

Quality (ISO 9001)

ITP 100% complete

NCRs

No non-conformances raised.

Material certs (mill certs)

No heats recorded yet.