VSBA Wilmont School Bundle
Zauner Construction · Shepparton VIC · PM Dan Kelly · 71 t
Complete
Due 20 Feb 2026
1 Won
2 Detailing
3 Fabrication
4 Surface Treatment
5 Ready to Dispatch
6 Installing
7 Complete
Job profitability, cost vs contract
23% marginContract (ex-GST)
$388,000
Final cost
$299,400
Margin
$88,600
Steel & sections $125,748
Fabrication labour $83,832
Surface treatment $23,952
Site install $41,916
Detailing & freight $23,952
Margin $88,600
Billing (Xero)
- Contract ex-GST
- $388,000
- GST (10%)
- $38,800
- Total inc-GST
- $426,800
- Invoiced to date
- $388,000
- Remaining to bill
- $0
- Progress
- 100%
Variations
$0 approvedNo variations raised on this job.
Progress claim
- Original contract
- $388,000
- Approved variations
- $0
- Adjusted contract
- $388,000
- Claimed to date
- $388,000
- Retention held (5%)
- $19,400
- This claim (100%)
- $0
Workshop, work orders (0)
No work orders yet, job still in detailing.
Purchasing, steel POs (0)
No purchase orders raised yet.
Quality (ISO 9001)
ITP 100% completeNCRs
- NCR-2026-010 Closed
Paint DFT below 125µm on 3 members
Material certs (mill certs)
No heats recorded yet.