VSBA Wilmont School Bundle

Zauner Construction · Shepparton VIC · PM Dan Kelly · 71 t

Complete Due 20 Feb 2026
1 Won
2 Detailing
3 Fabrication
4 Surface Treatment
5 Installing
6 Complete

Job profitability — live cost vs contract

23% margin

Contract (ex-GST)

$388,000

Final cost

$299,400

Margin

$88,600

Steel & sections $125,748
Fabrication labour $83,832
Surface treatment $23,952
Site install $41,916
Detailing & freight $23,952
Margin $88,600

Billing (Xero)

Contract ex-GST
$388,000
GST (10%)
$38,800
Total inc-GST
$426,800
Invoiced to date
$388,000
Remaining to bill
$0
Progress
100%

Workshop — work orders (0)

No work orders yet — job still in detailing.

Purchasing — steel POs (0)

No purchase orders raised yet.

Quality (ISO 9001)

ITP 100% complete

NCRs

  • NCR-2026-010 Closed

    Paint DFT below 125µm on 3 members

Material certs (mill certs)

No heats recorded yet.